http://www.gkong.com 2006-03-29 16:10 《中华工控网》翻译
ABB wins $65 million order to boost power reliability in
ABB赢得加州价值六千五百万美元电力订单
Substation upgrade and new substation will improve city’s transmission system
变电站的升级及新变电站的落成将改善城市的电力传输系统
Zurich, Switzerland, March 28, 2006 – ABB, the leading power and automation group, said today it has won a $65 million substation order that will increase the reliability of power supply in the city of Anaheim, California.
苏黎世3月28日消息—领先的电力和自动化集团ABB公司今天宣布获得了加州阿纳海姆价值六千五百万美元的变电站合同,提高该城市的电力供应可靠性。
ABB will upgrade an existing 230/69 kilovolt (kV) substation, build a new 230/69kV gas insulated switchgear substation, install a new transmission line between them and convert several kilometers of existing overhead power lines to underground cable.
ABB将升级一个现有的230/69千伏特变(KV)电站,建设一个新的230/69kV气体绝缘接电装置变电站,在这两个变电站之间安装一条新的传输线,并且现有的几千米高架电线改为地下电线。
“Our technology will help to ensure a reliable power supply to the city,” said Samir Brikho, head of ABB’s Power Systems division. “We are well positioned to take on projects of this scope, where the customer needs a complete package of technology and project management expertise.”
ABB电力系统部主管Samir Brikho 说:“我们的技术将帮助确保该市的电力供应可靠性。我们非常适合承担这种范围的项目,在这些项目中,客户要求完全的技术承包和项目管理专业技术。”
The Lewis 230kV Extension Project is the largest individual undertaking by Anaheim Public Utilities. The completed project will provide the city with a much-improved, reliable source of power along with aesthetic improvement of the electric facilities in and around the substations.
这个Lewis 230kV扩展项目是阿纳海姆公用事业中最大的单独任务。该项目的完工将给该市带来极大改善的可靠的电力供应,以及变电站周围美观的电力设施。
ABB will provide all engineering, equipment and material procurement, construction and commissioning on the project, which is scheduled for completion in under two years.
ABB将提供一切的工程,购买所有的设备和材料,建造和测试此项目。该项目计划在两年内完工。
ABB是电力和自动化技术领域的全球领导厂商,致力于为工业和电力行业客户提供解决方案,以帮助客户提高生产效率,同时降低对环境的不良影响。ABB集团的业务遍布全球100多个国家,拥有大约104,000名雇员。